Seventh Circuit Deals Major Blow To EPA’s New Source Review Enforcement

The U.S. Court of Appeals for the Seventh Circuit released its decision in United States v. Midwest Generation, LLC and held violations of the preconstruction permit requirements of the Clean Air Act’s New Source Review program are subject to a five-year statute of limitations.

United StatesEnvironment

On Monday, July 8, 2013, the U.S. Court of Appeals for the Seventh Circuit released its decision in United States v. Midwest Generation, LLC and held violations of the preconstruction permit requirements of the Clean Air Act's New Source Review program are subject to a five-year statute of limitations. The Court rejected U.S. EPA's argument that violations of the New Source Review preconstruction permitting requirements, specifically 42 U.S.C. §7475(a), are "continuing violations." The Seventh Circuit is the fourth Federal Appellate Court to take up this longstanding issue, and the decision bolsters arguments the regulated community has been making for years. The decision is an important win for the regulated community and may help curtail U.S. EPA's New Source Review enforcement. However, the Seventh Circuit left open alternative arguments U.S. EPA could make in some New Source Review enforcement cases, so the full impact of the decision is not yet clear.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from