ARTICLE · 23 JULY 2014

Settling Parties In Government Consent Orders Have CERCLA Claims For Contribution Not Cost Recovery

The Sixth Circuit has now made crystalline that a party settling some or all of its liability under CERCLA with the United States or a state has a contribution claim under Section 113.

United StatesEnvironment

To the extent there was any remaining uncertainty, the Sixth Circuit has now made crystalline that a party settling some or all of its liability under CERCLA with the United States or a state has a contribution claim under Section 113 and not a cost recovery action under Section 107. Additionally, that contribution claim must be brought within three years of the date of any judgment entering the settlement or of any administrative order memorializing the settlement. No "if, ands, or buts."

The Sixth Circuit decision was Hobart Corporation v. Waste Management of Ohio, Inc. It involved three PRPs who entered into an Administrative Settlement Agreement and Order on Consent with the US EPA to perform the RI/FS at an Ohio Landfill and to pay certain of the government's costs. Almost four years later, the settling parties first brought an action against other PRPs who had also used the landfill. That action asserted both cost recovery and contribution claims. Noting that a

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.