New York Legislature Passes First-In-The-Nation Data Center Moratorium, Awaiting Governor’s Signature

Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.
Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.
Contributor
Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.

Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.

Mintz is a litigation powerhouse and business accelerator serving leaders in life sciences, private...

View firm profile
Explore more from Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C.

The moratorium exempts modifications or renewals of previously issued approvals and projects that commence construction by the effective date, and separately subjects existing, newly operational, and expanding data centers to energy-efficiency, host-community benefit, labor, rate-classification, and environmental-review obligations.

United StatesEnvironment

On June 4, 2026, the New York Legislature passed the Responsible Data Center Development Act (A11560/S10642).

The bill is a one-year moratorium on permits for “large data centers,” meaning data centers with peak demand of 20 megawatts (MW) or more. In addition, the bill would require an environmental impact report, as well as new labor, energy efficiency, transparency standards, and ratepayer protections. The moratorium exempts modifications or renewals of previously issued approvals and projects that commence construction by the effective date, and separately subjects existing, newly operational, and expanding data centers to energy-efficiency, host-community benefit, labor, rate-classification, and environmental-review obligations.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from