On June 4, 2026, the New York Legislature passed the Responsible Data Center Development Act (A11560/S10642).
The bill is a one-year moratorium on permits for “large data centers,” meaning data centers with peak demand of 20 megawatts (MW) or more. In addition, the bill would require an environmental impact report, as well as new labor, energy efficiency, transparency standards, and ratepayer protections. The moratorium exempts modifications or renewals of previously issued approvals and projects that commence construction by the effective date, and separately subjects existing, newly operational, and expanding data centers to energy-efficiency, host-community benefit, labor, rate-classification, and environmental-review obligations.