New Regulations Expedite New York Article VII Proceedings For Certain Proposed Electric Transmission Lines

In April 2021, the New York Public Service Commission amended its regulations under Article VII of the Public Service Law to accelerate the review and approval process for certain major electric utility transmission facilities.

United StatesEnvironment

Introduction

In April 2021, the New York Public Service Commission (PSC) amended its regulations under Article VII of the Public Service Law (PSL) to accelerate the review and approval process for certain major electric utility transmission facilities. Entitled "Procedures with Respect to Expedited Proceedings," the new regulations are codified as Subpart 85-3 of the PSC's regulations at Title 16 of the New York Code, Rules and Regulations (NYCRR). The new regulations are the result of a PSC rulemaking process commenced in September 2020 in Case 20-T-0288. This Client Alert summarizes and comments on the new regulations.

The Accelerated Renewable Energy Growth and Community Benefit Act (Act),1 enacted in April 2020, required the PSC to promulgate rules that would establish an "expedited process" for certain Article VII applications. The Act defined such a process as one "that is completed in all respects, including a final decision by the commission, within

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from