Federal Appeals Court Upholds Army Corps’ Economic Analysis For Issuance Of Wetlands Permit

In Sierra Club v. Van Antwerp, decided by the U.S. Court of Appeals for the District of Columbia Circuit, the Army Corps of Engineers approved a permit under the Clean Water Act (the Act) authorizing the fill of approximately 54 acres of wetlands for the construction of a large town center outside of Tampa, Florida.

United StatesEnvironment

In Sierra Club v. Van Antwerp, decided by the U.S. Court of Appeals for the District of Columbia Circuit, the Army Corps of Engineers approved a permit under the Clean Water Act (the Act) authorizing the fill of approximately 54 acres of wetlands for the construction of a large town center outside of Tampa, Florida.  In issuing the permit, the Corps found that the alternatives to the project—such as reducing its size to lessen the impacts to wetlands—were impracticable for economic reasons.  While the court found some minor deficiencies in the permit, it upheld the Corps' economic analysis and reversed the lower court's finding that this analysis violated the Act.

Under the Clean Water Act and its implementing regulations, the Corps may issue a wetlands permit for a project only if no practicable alternative to the project exists that is less damaging to the aquatic system.  An alternative is practicable "if it is available and capable of being done after taking

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from