ARTICLE · 26 JUNE 2026

Environmental Protection Agency Proposes Flexibility For Pre-Permit Construction Under Clean Air Act New Source Review

K&L Gates
K&L Gates
Contributor
K&L Gates

K&L Gates

The Firm K&L Gates is an integrated, international law firm. As a single global law firm, truly...

View firm profile
Explore more from K&L Gates

On 13 May 2026, the Environmental Protection Agency (EPA) issued proposed rule, “Begin Actual Construction in the New Source Review (NSR) Preconstruction Permitting Program” (91 Fed. Reg. 26958) (Proposed Rule)...

United StatesEnvironment

On 13 May 2026, the Environmental Protection Agency (EPA) issued proposed rule, “Begin Actual Construction in the New Source Review (NSR) Preconstruction Permitting Program” (91 Fed. Reg. 26958) (Proposed Rule), which seeks to streamline the Clean Air Act’s NSR preconstruction permitting program by allowing source owners or operators to begin certain physical non-emitting construction activities prior to obtaining an NSR permit. If finalized, the Proposed Rule would narrow the scope of activities falling within the scope of “begin actual construction,” allowing for accelerated construction timelines for a wide array of energy and infrastructure projects—including power plants, data centers, petrochemical facilities, and other industrial and manufacturing facilities that require air permits.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from