District Court Rejects Challenge To Wind Farm Permitting, Finds No Violation Of ESA Or Eagle Protection Act

BakerHostetler
BakerHostetler
Contributor
BakerHostetler

BakerHostetler

Recognized as an innovator and one of the top firms for client service, BakerHostetler helps...

View firm profile
Explore more from BakerHostetler

This month a federal court in Maine rejected a challenge to a permit issued by the U.S. Army Corps of Engineers (Army Corps) for the Oakfield wind power project.

United StatesEnvironment

This month a federal court in Maine rejected a challenge to a permit issued by the U.S. Army Corps of Engineers (Army Corps) for the Oakfield wind power project. The court determined that the Army Corps did not violate the Endangered Species Act (ESA) or the Bald and Golden Eagle Protection Act (Eagle Protection Act) in issuing the permit. The court's decision is part of a growing trend of cases concluding that a federal agency's obligations under the Eagle Protection Act and Migratory Bird Treaty Act are limited where the agency permits or authorizes a private project.

In Protect Our Lakes v. U.S. Army Corps of Engineers, No. 13-cv-402 (D. Me. Feb. 20, 2015), the plaintiffs filed suit against the Army Corps over the issuance of a Clean Water Act Section 404 permit that authorized the Oakfield wind project developer to permanently and temporarily fill in certain wetlands during project construction. The plaintiffs challenged the permit on a number of grounds, but