Far too frequently, we are reminded just how hard judges must
work to save CERCLA from itself. The decision last week in
California River Watch v. Fluor Corporation is the most
recent compelling example.
Fluor Corporation has been performing response actions at a
site, including operating a soil vapor extraction system, since no
later than 1997. Fluor's remedial action plan was not
approved until 2011 and a modified RAP was approved in 2014.
As readers here will know, CERCLA provides that claims based on
removal actions must be brought within three years of completion of
the removal action, while claims based on remedial actions must be
brought within six years of commencement of on-site
construction. The question in California River Watch was of
course whether Fluor's treatment system was a removal action or
a remedial action. The jurisprudential answer here was easy
– 9th Circuit precedent holds that, by definition,
a remedial action cannot start until