After a nearly two-year wait, in Protecting Our Water and Environmental Resources v. County of Stanislaus (2020) __ Cal.5th ____ (POWER)

United StatesEnvironment

After a nearly two-year wait, in Protecting Our Water and Environmental Resources v. County of Stanislaus (2020) __ Cal.5th ____ (POWER), the California Supreme Court unanimously rejected the County of Stanislaus's (County) bright-line categorization that all groundwater well construction permits are ministerial, and therefore not subject to the California Environmental Quality Act (CEQA). In an interesting twist, the Supreme Court also rejected the petitioner's alternative "all or nothing" position that, if the permits are not ministerial, they must be discretionary and conditioned on CEQA compliance. Instead, the Supreme Court held the decision of whether each permit is ministerial or discretionary hinges on the specific language of the governing ordinance and regulatory controls.1

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from