The Sixth District Court of Appeal, in Pfeiffer v. Sunnyvale, recently upheld the use of a traffic baseline that included future projects despite an earlier Sixth District case that had raised serious questions about that practice.

United StatesEnvironment

The Sixth District Court of Appeal, in Pfeiffer v. Sunnyvale, recently upheld the use of a traffic baseline that included future projects despite an earlier Sixth District case that had raised serious questions about that practice.

Traffic engineers preparing an Environmental Impact Report had a long-standing practice of evaluating the traffic impacts of a project by asking whether roadways could accommodate project-generated traffic under the circumstances that were expected to exist when the project would be constructed and generating traffic. A typical formulation would be to assess a background level consisting of existing traffic plus traffic from approved but not yet built projects and anticipated growth, and then compare that background level to the traffic circumstances that would be expected when project-generated traffic was added. The background level of traffic typically would not exist until after project approval.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from