Rooftop PV power projects having a capacity of under 1 MW are not subject to procedure to amend the Power Master Plan.

United StatesEnergy and Natural Resources

Rooftop PV power projects having a capacity of under 1 MW are not subject to procedure to amend the Power Master Plan. The investor only needs to register the connecting terminal with a provincial power company and provide general information about expected capacity, specifications of solar panels and the power inverter.

Rooftop PV power projects having a capacity of 1 MW or over must be included in the master or provincial Power Master Plan. In addition, they must obtain the license for generating electricity.

There is a standard PPA for rooftop PV projects between the seller and EVN in Circular 16/2017/TT-BCT by the MOIT. Although the Investment Law does not prohibit investment in the form of a direct PPA, a direct off-grid PPA between the investor and the buyer other than EVN is still pending for further guidance now being worked on by the Electricity Regulatory Authority of Vietnam ("ERAV"). Our contacts in the ERAV informed us that these new rules might come