Share on LinkedInShare on LinkedIn

ARTICLE · 22 MAY 2017

RTOs/ISOs Submit Order No. 831 Compliance Filings

The May 8, 2017 compliance filings were specifically tailored to each RTO/ISO, and the proposed implementation timeframes proposed by each RTO/ISO varied considerably.

United StatesEnergy and Natural Resources

On May 8, 2017, the nation's Regional Transmission Organizations and Independent System Operators ("RTOs/ISOs") submitted their respective compliance filings to implement the directives from FERC Order No. 831, which revised FERC's regulations regarding incremental energy offer caps imposed by RTOs/ISOs.

In Order No. 831, FERC required RTOs/ISOs to cap each resource's "incremental energy offer"—the portion of an energy resource's supply market offer that can vary depending on output or demand levels—at the higher of $1,000/megawatt-hour ("MWh") or that resource's verified actual or expected cost-based incremental energy offer.  FERC also required RTOs/ISOs to cap verified cost-based incremental energy offers at $2,000/MWh when calculating locational marginal prices ("LMP") (see November 21, 2016 edition of the WER).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from