More Detail On The Massachusetts DG Interconnection Docket

On Monday, August 19, the Massachusetts Department of Public Utilities ("DPU") provided additional information on the timing, process, and scope of its investigation into DG interconnection

United StatesEnergy and Natural Resources

On Monday, August 19, the Massachusetts Department of Public Utilities ("DPU") provided additional information on the timing, process, and scope of its investigation into DG interconnection. The full memorandum from the Hearing Officer is here. This procedural update follows the July 18 technical conference, which we summarized here. A few key points from the memorandum:

  • Three additional technical conferences have been scheduled in the docket for October 3, October 24, and November 21. The topics for those conferences are not yet set.
  • The DPU is holding bi-weekly meetings with National Grid, New England Power, and ISO-NE regarding National Grid's "Cluster Study". The DPU is "working on creative methods to remove certain DG facilities from the Cluster Study," and will provide updates to the DPU 19-55 electronic distribution list. We will have to wait to see what this means and whether it bears fruit.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from