FERC Issues Final Rule Regarding Gas-Electric Coordination

On April 16, 2015, FERC issued Order No. 809, "Coordination of the Scheduling Processes of Interstate Natural Gas Pipelines and Public Utilities.

United StatesEnergy and Natural Resources

On April 16, 2015, FERC issued Order No. 809, "Coordination of the Scheduling Processes of Interstate Natural Gas Pipelines and Public Utilities," in furtherance of its goal to improve the coordination of wholesale natural gas and electricity market scheduling in order to ensure the reliable and efficient operation of the nation's natural gas pipeline and electric systems.  In issuing Order No. 809, FERC explained that as the nation increasingly relies on natural gas for electric generation, FERC has identified a mounting concern related to this growing gas-electric interdependence and a misalignment between the gas and electric operating days.

Order No. 809 follows a March 20, 2014 Notice of Proposed Rulemaking ("NOPR") (see March 21, 2014 edition of the WER), which proposed to amend FERC's rules relating to the scheduling of transportation service on interstate natural gas pipelines in order to (i) better coordinate with the scheduling practices of the electric

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from