ARTICLE · 19 SEPTEMBER 2023

FERC Implements Generator Interconnection Process Reforms: Compliance Filings Due December 2023

On September 6, 2023, the Federal Register published the Federal Energy Regulatory Commission's (FERC) Order No. 2023, ‘Improvements to Generator Interconnection Procedures and Agreements...

United StatesEnergy and Natural Resources

On September 6, 2023, the Federal Register published the Federal Energy Regulatory Commission's (FERC) Order No. 2023, 'Improvements to Generator Interconnection Procedures and Agreements,' a 1,000+ page Final Rule adopting reforms to generator interconnection procedures and amending the pro forma Large Generator Interconnection Procedures (LGIP), the pro forma Large Generator Interconnection Agreement (LGIA), the Small Generator Interconnection Procedures (SGIP) and the Small Generator Interconnection Agreement (SGIA).1 Responding to more than 4,500 pages of comments, FERC adopted most of its proposals from its June 16, 2022 Notice of Proposed Rulemaking ("NOPR").2

Order No. 2023 is FERC's attempt to address widely reported backlogs in generation interconnection queues across the country and cost uncertainty related to necessary transmission system upgrades to accommodate new interconnections. FERC's companion NOPR on transmission expansion and associated cost

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from