FERC Grants CAISO Waiver For Acquired Resources In RAAIM

On April 30, 2018, the Commission granted the California Independent System Operator Corporation's ("CAISO") request for a limited waiver of a specific section of CAISO's Tariff ...

United StatesEnergy and Natural Resources

On April 30, 2018, the Commission granted the California Independent System Operator Corporation's ("CAISO") request for a limited waiver of a specific section of CAISO's Tariff to allow CAISO to: (1) process out-of-time annual recertifications for certain resources as "Acquired Resources" for the 2018 resource adequacy compliance year, and (2) provide certainty to those resources that their Resource Adequacy Availability Incentive Mechanism ("RAAIM") exemption for the 2017 resource adequacy compliance year will not be unwound.

In 2009, CAISO developed the resource adequacy Standard Capacity Product, which provided a standard definition for resource adequacy with defined performance incentives.  The Standard Capacity Product exempted certain resources (known as "Acquired Resources") from the aforementioned performance incentives if the associated resource supply contract existed prior to June 28, 2009 — the theory being that such existing contracts likely contained

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from