FERC Directs Revisions To Enable Co-Located Load (Data Centers) And Generation

Sheppard
Sheppard
Contributor
Sheppard

Sheppard

Businesses turn to Sheppard to deliver sophisticated counsel to help clients move ahead. With more...

View firm profile
Explore more from Sheppard

On December 18, 2025, the Federal Energy Regulatory Commission (FERC) took a significant step to break up the log jam that is precluding large load and data centers to receive power in the PJM Interconnection...

United StatesEnergy and Natural Resources

On December 18, 2025, the Federal Energy Regulatory Commission (FERC) took a significant step to break up the log jam that is precluding large load and data centers to receive power in the PJM Interconnection, L.L.C. (PJM) region of the United States.1 FERC issued an Order finding that PJM's existing rules that pertain to generation that interconnects with load behind the point of interconnection (BTMG) are unjust and unreasonable and must be revised. FERC's directives to PJM likely signal what FERC may require in some form throughout the nation.

There are many sub-parts and requirements that FERC directed, but in general FERC's directives fall into two categories.

First, BTMG should be evaluated by PJM only to the extent of actual intended injection to the grid. FERC explains that, if a 1,000 MW generator will use 900 MW to serve co-located load and lean on the PJM transmission grid for only 100 MW, then PJM need only study the 100 MW.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from