FERC Determines Residue Line In Operation Since 1969 Is Jurisdictional

The Coyanosa Residue Line is an 8.1-mile-long pipeline in Pecos County, Texas. The pipeline transports gas from the outlet of Regency's Coyanosa processing plant to four intrastate pipelines and one interstate pipeline.

United StatesEnergy and Natural Resources

On October 15, 2015, FERC issued a certificate of public convenience and necessity under section 7(c) of the Natural Gas Act ("NGA") and a blanket certificate under Part 157 of the FERC's regulations to Regency Field Services LLC ("Regency") to continue operating the existing Coyanosa Residue Line.  In issuing the certificates, FERC held that the Coyanosa Residue Line was jurisdictional under FERC's current five-mile processing plant "stub line" test, even though the line was in operation well before FERC adopted the test in 1994.

The Coyanosa Residue Line is an 8.1-mile-long pipeline in Pecos County, Texas.  The pipeline transports gas from the outlet of Regency's Coyanosa processing plant to four intrastate pipelines and one interstate pipeline.  The Coyanosa Residue Line was placed into service in 1969, replaced in 2000, acquired by Regency in 2013, and has always carried processed gas from the Coyanosa processing plant to interstate and intrastate pipelines.  On

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from