On August 31, 2018, the Federal Energy Regulatory Commission
("Commission") issued an order ("August 31
Order") in which it denied a complaint
("Complaint") by the California Public Utilities
Commission, Northern California Power Agency, City and County of
San Francisco, the State Water Contractors, and the Transmission
Agency of Northern California (collectively,
"Complainants") against Pacific Gas and Electric Company
("PG&E"). Complainants alleged that PG&E
was in violation of its obligation under Order No. 890 to conduct
an open, coordinated, and transparent transmission planning process
because, according to Complainants, more than 80 percent of
PG&E's transmission planning is done on an internal basis
without opportunity for stakeholder input or review. In Order
No. 890, the Commission found, among other things, that in order
for a Regional Transmission Organization or Independent System
Operator's transmission planning processes to be open and
transparent,