FERC Declaratory Orders In Sun Edison LLC And JD Wind Companies Boost Wind And Solar Projects

FERC’s two separate declaratory rulings confirming that intermittent renewable power generation is entitled to certain PURPA benefits and that sales by a developer of onsite solar generation to end-use customers do not constitute jurisdictional activities provide important regulatory clarity to renewable power developers further boosting the prospects of such projects.

United StatesEnergy and Natural Resources

FERC's two separate declaratory rulings confirming that intermittent renewable power generation is entitled to certain PURPA benefits and that sales by a developer of onsite solar generation to end-use customers do not constitute jurisdictional activities provide important regulatory clarity to renewable power developers further boosting the prospects of such projects.

On November 19, 2009, the Federal Energy Regulatory Commission (FERC) issued an order declaring as inconsistent with the requirements of the Public Utility Regulatory Policies Act of 1978 (PURPA) and related FERC rules (particularly Section 292.304(d)) a May 1, 2009, decision of the Public Utility Commission of Texas (PUCT) that the wind-powered generation of the JD Wind Companies (JD Wind) is not entitled to a legally enforceable obligation and an avoided cost rate calculated when that obligation is incurred. FERC issues this order instead of initiating an enforcement action against the PUCT. Several

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from