Share on LinkedInShare on LinkedIn

ARTICLE · 17 OCTOBER 2016

FERC Clarifies Order No. 827 Reactive Power Requirements For Newly Interconnecting Non-Synchronous Generators

Order No. 827's reactive power requirements for newly interconnecting non-synchronous generators do not apply to all existing non-synchronous generators making upgrades that require interconnection requests.

United StatesEnergy and Natural Resources

On October 3, 2016, FERC clarified that Order No. 827's reactive power requirements for newly interconnecting non-synchronous generators do not apply to all existing non-synchronous generators making upgrades that require interconnection requests. FERC further clarified that, instead, transmission providers may propose changes to their tariffs to define "newly interconnecting non-synchronous generators" to include repowering an existing generator. 

In Order No. 827, FERC required all newly interconnecting non-synchronous generators, including wind generators, to design their facilities to be capable of providing reactive power (see June 20, 2016 edition of the WER). FERC did not apply Order No. 827's requirements to existing generators making upgrades that require new interconnection requests because, according to FERC, the generators may not be installing equipment capable of providing reactive power, and requiring those generators to make further upgrades to be

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from