In an April 29, 2016 order regarding cost allocation among the
Entergy operating companies, FERC clarified and distinguished its
approach to refunds in cost allocation and rate design cases, from
its approach to refunds in cases of utility over-recovery
("April 29 Order"). Specifically, FERC clarified that it
will generally decline to order refunds under disputes over cost
allocation, whereas refunds will generally be awarded in cases
involving allegations of a utility earning more than a just and
reasonable rate during the refund period.
The proceedings at issue originated in 1995, when the Louisiana
Public Service Commission ("LPSC") filed a complaint at
FERC alleging that certain cost allocation calculations used by
Entergy Services, Inc. under the Entergy System Agreement—an
agreement between and among the Entergy operating
companies—were unjust and unreasonable because they did not
exclude interruptible load from the calculation of peak load
responsibility. On