ARTICLE · 07 JULY 2014

FERC Approves Reliability Standard On Geomagnetic Disturbances

Among other requirements in the new standard, applicable Transmission Operators must develop and implement operating procedures to mitigate GMD effects.

United StatesEnergy and Natural Resources
J. Daniel Skees
J. Daniel Skees

FERC has approved a new Reliability Standard to address Geomagnetic Disturbances (GMDs). EOP-010-1 (Geomagnetic Disturbance Operations) is the first in a set of Reliability Standards addressing the threat of GMDs to bulk-power system reliability. FERC's concern with GMDs has been that they can create geomagnetically induced currents in transformers, which can, in turn, increase the absorption of reactive power, create harmonics, and cause transformer spot-heating. Ultimately, the loss of reactive power this causes could result in voltage instability, relay misoperations, and equipment damage.

As written, the new standard applies to (a) Transmission Operators whose Transmission Operator Area includes a power transformer with a high side, wye-grounded winding with terminal voltage greater than 200 kV and (b) Reliability Coordinators.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from