On 22 May 2023, the Federal Energy Regulatory Commission (FERC) issued two orders approving stipulation and consent agreements that resolve enforcement investigations by FERC's Office of Enforcement...

United StatesEnergy and Natural Resources

On 22 May 2023, the Federal Energy Regulatory Commission (FERC) issued two orders approving stipulation and consent agreements that resolve enforcement investigations by FERC's Office of Enforcement (FERC Enforcement) of two demand response providers, Leapfrog Power, Inc. (Leapfrog) and OhmConnect, Inc. (OhmConnect), regarding their participation in the California Independent System Operator (CAISO) market.1FERC Enforcement's focus in both cases concerned whether the companies violated a provision of the CAISO tariff requiring market participants to have a reasonable expectation that they could fulfill the bids they submitted.

Background

Demand response providers contract with end-use customers who agree, when requested, to reduce the amount of electric power they would otherwise typically consume. In California, demand response providers aggregate demand response pursuant to a Demand Response Auction Mechanism (DRAM) pilot program administered by the California

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from