FERC Accepts MISO's Revisions to Generator Interconnection Procedures

On January 3, 2017, FERC accepted the Midcontinent Independent System Operator, Inc.'s ("MISO") proposed revisions to its Generator Interconnection Procedures ("GIP")...

United StatesEnergy and Natural Resources

On January 3, 2017, FERC accepted the Midcontinent Independent System Operator, Inc.'s ("MISO") proposed revisions to its Generator Interconnection Procedures ("GIP") and its pro forma Generator Interconnection Agreement ("GIA") contained in Attachment X of its Open Access Transmission, Energy and Operating Reserve Markets Tariff ("Tariff"). MISO's revisions result from an extensive stakeholder process intended to improve the efficiency of its queue for generator interconnection projects.

MISO filed its proposed revisions on October 21, 2016. MISO proposed revisions intended to minimize restudies and incentivize interconnecting customers to advance projects through the queue efficiently, or withdraw projects in a timely manner where appropriate. Specifically, MISO proposed to divide its existing Definitive Planning Phase ("DPP") into three phases, each of which will require the interconnecting customer to pay a milestone payment that will be refundable subject to

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from