On March 10, 2021, the Massachusetts Department of Public Utilities (DPU) issued a memorandum regarding additional procedural steps in its distributed generation (DG) interconnection docket – D.P.U. 19-55.

United StatesEnergy and Natural Resources

On March 10, 2021, the Massachusetts Department of Public Utilities (DPU) issued a memorandum regarding additional procedural steps in its distributed generation (DG) interconnection docket - D.P.U. 19-55.   As we previously discussed, this docket seeks to investigate issues associated with interconnection of DG projects.  As next steps for this docket, the DPU memorandum notes:

  • Cost allocation considerations for DG interconnection costs will proceed under DPU docket 20-75;
  • The investigation into affected system operator studies is complete, but reporting and the process developed for those studies will continue;
  • The DPU will continue its investigation into timelines for interconnection, starting with specific questions posed to the Electric Distribution Companies related to the scope of delays in DG interconnection;

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from