On 23 October 2025, Department of Energy (DOE) Secretary Chris Wright asked the Federal Energy Regulatory Commission (FERC) to consider an Advance Notice of Proposed Rulemaking (ANOPR) for the interconnection of retail loads greater...

United StatesEnergy and Natural Resources

On 23 October 2025, Department of Energy (DOE) Secretary Chris Wright asked the Federal Energy Regulatory Commission (FERC) to consider an Advance Notice of Proposed Rulemaking (ANOPR) for the interconnection of retail loads greater than 20 MW to jurisdictional transmission facilities.1 DOE expects FERC to take final action not later than 30 April 2026.

In issuing the letter and proposed rule, Secretary Wright explained that unprecedented and extraordinary quantities of electricity and substantial investment in the nation's interstate transmission system are necessary to meet the Trump administration's commitment to revitalizing domestic manufacturing and driving American artificial intelligence innovation. Secretary Wright points to the fact that electricity demand is expected to grow at an extraordinary pace due in large part to the rapid growth of large loads and the unique challenges presented by the size and speed with which data centers can be connected to

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from