ARTICLE · 29 OCTOBER 2025

DOE Directs FERC To Initiate Large Load Interconnection Rulemaking

Akin
Akin
Contributor
Akin

Akin

Akin is a global law firm with more than 1,100 lawyers and advisors who pride themselves on...

View firm profile
Explore more from Akin

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric...

United StatesEnergy and Natural Resources

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC's rulemaking process. The Secretary has directed FERC to take "final action" on the Directive no later than April 30, 2026.

Citing "unprecedented and extraordinary" electricity demand driven by the rapid proliferation of data centers, onshoring of manufacturing, and trends in electrification, the Directive would have FERC address the lack of standardized rules governing how large loads—which it preliminarily defines

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from