For projects that involve excavation or foundation work, even
the most diligent pre-bid site survey may not fully inform the
contractor of what conditions to expect below the surface. The
risks of encountering unforeseen subsurface conditions are so high
that, rather than encouraging bidders to include large
contingencies in their proposals, construction lawyers have drafted
a special clause-the Differing Site Conditions clause. The purpose
of the Differing Site Conditions clause is to allocate the risk for
conflicting, inaccurate, or incomplete pre-bid information
furnished by the project owner. While the Differing Site Conditions
Clause should, in theory, be a pile driver's closest ally,
recent cases interpreting this clause highlight some of the
challenges to prosecuting claims under this provision.