The doctrine of “first material breach” is well
established under Tennessee case law. Under the doctrine,
“[a] party who has materially breached a contract is not
entitled to damages stemming from the other party's later
material breach of the same contract.”1 In
cases where both parties to a contract have not fully performed, a
court must determine which party is chargeable with the
“first uncured material breach.”2 In
determining such, a court's analysis can be broken down into
three distinct steps.
First, a court must determine what the contract required of the
parties, which is a “question of
law.”3 Second, a court must determine
“[w]hether a party has fulfilled its obligations under [the]
contract or is in breach of the contract,” which is a
question of fact.4 Third, a court must determine
whether a party's breach is “material,” which is
also a question of fact.5