ARTICLE · 02 APRIL 2026

The “But For” Dilemma – How Proposed Texas Public Utility Commission Large Load Interconnection Rules Impact Government Incentives Strategies

Companies seeking governmental incentives for expansion or relocation projects, such as tax abatements or state-level grants, must typically demonstrate that the project would not be viable “but for” the receipt of those incentives.

United StatesCorporate/Commercial Law

Companies seeking governmental incentives for expansion or relocation projects, such as tax abatements or state-level grants, must typically demonstrate that the project would not be viable “but for” the receipt of those incentives.

The Public Utility Commission of Texas (PUCT) has proposed Rule 16 TAC §25.194, which mandates early-stage financial commitments, site control, and transparency for projects requiring a large load interconnection request (75 MW or larger). Entities seeking incentives for large load projects will need to be mindful of these requirements to make a strong and clear “but for” case.

Below is an analysis of how these proposed requirements fundamentally shift the timing and disclosure landscape for expansion and relocation project development.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from