ARTICLE · 24 JULY 2015

Liquidated Damages Can Create A Cap On What You Can Recover

After Clark paid KGM the $595,000 settlement amount, KGM sought to collect the $375,000 in liquidated damages it was owed by the Proskys.

United StatesCorporate/Commercial Law

When thinking about liquidated damages, most people focus on the fact that a properly drafted liquidated damages provision will enable the non-breaching party to recover a set amount without ever having to prove how much, if any, actual damages were incurred. What people often forget to consider, however, is that a liquidated damages clause also sets a ceiling for damages.

In K.G.M. Custom Homes, Inc. v. Prosky, the plaintiff prevailed on a breach of contract claim against the defendants when their counsel engaged in conduct that prevented KGM from closing on the purchase of real estate that it had contracted to buy from them. As a result, KGM was awarded $375,000 in damages, the liquidated amount called for by the purchase and sale agreement if the Proskys did not complete the transaction.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from