This is the second post in our series addressing mechanic's liens in Texas on private commercial/non-residential projects.

United StatesCorporate/Commercial Law

Post #2 in our Series on Private Non-Residential/Commercial Mechanic's Liens in Texas

This is the second post in our series addressing mechanic's liens in Texas on private commercial/non-residential projects. In the last post, we discussed the difference between original contractors and subcontractors. As a reminder, an original contractor is a person/company contracting directly with the property owner.1 In this post, we discuss the steps necessary for an original contractor to perfect a mechanic's lien.

Unlike subcontractors, original contractors are not required to send pre-lien notices informing the owner of the lack of payment for work or materials provided on a project.  The policy rationale behind not requiring pre-lien notices focuses on the direct contractual relationship between the owner and the original contractor.  Because the owner and original contractor are interacting directly, if there is a payment dispute, both parties should already be aware

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from