Delay Days For Liquidated Damages May Be Apportioned Where Permitted By Contract
Ballard Spahr LLP
Overlapping delays partly caused by a contractor and partly by an owner — known as concurrent delays — typically nullify the assessment of liquidated damages in a breach of contract dispute.