ARTICLE · 29 NOVEMBER 2018

BritNed Developments v. Abb Revisited: UK High Court Rules Further Reduction In Damages And No Order As To Costs In Follow-On Competition Litigation

Arnold & Porter
Arnold & Porter
Contributor
Arnold & Porter

Arnold & Porter

With over 1,000 lawyers across 16 offices worldwide, Arnold & Porter is renowned for its...

View firm profile
Explore more from Arnold & Porter

On 9 October 2018, the High Court of England and Wales awarded BritNed Developments damages of just over €13 million in the first cartel follow-on damages claim in the jurisdiction.

United StatesAntitrust/Competition Law

On 9 October 2018, the High Court of England and Wales awarded BritNed Developments damages of just over €13 million in the first cartel follow-on damages claim in the jurisdiction. BritNed had claimed €180 million in damages caused by ABB's participation in the power cables cartel. We summarized the Court's original judgment in our previous Advisory.

In two further judgments dealing with consequential matters, the High Court reduced BritNed's damages award by a further 10%, and ruled that in the circumstances of this case each party to the litigation should bear its own costs.

The Supplemental Judgment

In the 9 October judgment, the High Court had considered issues relating to a regulatory cap on BritNed's earnings imposed by UK and Dutch energy regulators. ABB argued that the damages awarded to BritNed would have the effect of overcompensation for its losses by exceeding the regulatory cap. The Court held that any collateral benefit to BritNed should be