ARTICLE · 05 DECEMBER 2012

Liens On Sub-Hire Under Standard Form NYPE 1946: Not Permitted

The New York Produce Exchange (NYPE) 1946 time charterparty form remains highly popular in bulk shipping.

United KingdomTransport

The New York Produce Exchange (NYPE) 1946 time charterparty form remains highly popular in bulk shipping. Following the High Court's decision in Dry Bulk Handy Holding Inc & another v Fayette International Holdings Ltd & another [2012] EWHC 2107 (Comm) ("BULK CHILE"), however, it is now clear that one of the key weapons in the owners' armoury when dealing with unpaid hire – namely the exercise of a lien on sub-hire – is unavailable on the standard wording of NYPE 1946.

Background

Clause 18 of the standard form NYPE 1946 stipulates that "the Owners shall have a lien upon all cargoes, and all sub-freights for any amounts due under this Charter". If the charterers' obligation to pay hire is as set out in clause 5 of the standard form, payment must be made by the charterers to the owners "semi-monthly in advance" – and if it is not so paid, the hire becomes an "amount due under this Charter", triggering the provisions of clause 18.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from