Arrival Periods Under CIF/CFR Contracts

In CIF/CFR contracts, buyers must monitor shipment dates, as arrival periods only ensure the seller ships goods timely. Late arrivals due to unforeseen events don't justify rejecting goods.

United KingdomTransport

Buyers still need to look shipment date

Understandably, where a CIF/CFR contract provides for an arrival period, it is often assumed that the vessel must arrive at the discharge port within that time. However, it is not normally as simple as that. Instead, the provision for an arrival period usually only means that the seller is obliged to ship the goods in order to ensure that, in the ordinary course of events, the vessel will arrive at the discharge port within that period.

The buyer must therefore still keep a close eye on the shipment date for the goods in order to act promptly on any breach by the seller and, equally, in order to avoid wrongfully rejecting the goods if the vessel arrives after the expiry of the arrival period due to circumstances beyond the seller's control.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from