Variations And Procedural Requirements Under The FIDIC Yellow Book

Bryan Cave Leighton Paisner
Bryan Cave Leighton Paisner
Contributor
Bryan Cave Leighton Paisner

Bryan Cave Leighton Paisner

UK 2026 Chambers Firm Profile Bryan Cave Leighton Paisner (BCLP) is an international, fully...

View firm profile
Explore more from Bryan Cave Leighton Paisner

What happens under a FIDIC Yellow Book 1999 when the Engineer approves a variation and the varied work is carried out but both Engineer and Contractor fail to follow the relevant contractual procedures...

United KingdomReal Estate and Construction

Summary

What happens under a FIDIC Yellow Book 1999 when the Engineer approves a variation and the varied work is carried out but both Engineer and Contractor fail to follow the relevant contractual procedures? Is the Contractor still entitled to payment?

These are the tricky questions which faced the Judicial Committee of the Privy Council (Board) in the case of Uniform Building Contractors Ltd v The Water and Sewerage Authority of Trinidad and Tobago (Trinidad and Tobago) [2026] UKPC 2.

What happened? 

The Water and Sewerage Authority of Trinidad and Tobago (WASA) entered into a lump sum contract (an amended FIDIC Yellow Book 1999) with Uniform Building Contractors Ltd (UBC) to design, supply and install a pipeline.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from