Transmission Connection Reform: Impact On Data Centres

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

A power connection is a critical ingredient for any data centre project, and in recent years in Great Britain it has become harder to obtain the power than the land required to develop facilities.

United KingdomReal Estate and Construction

A power connection is a critical ingredient for any data centre project, and in recent years in Great Britain it has become harder to obtain the power than the land required to develop facilities. It is now apparent that the existing approach to power connections in Great Britain is no longer fit for purpose. The regulator Ofgem has itself acknowledged that the waiting times for new connections are too long and this is one of the factors holding back data centre development.

As part of the UK Government's current focus on data centre development (in part to support its AI strategy), the National Energy System Operator (NESO) has been tasked with reforming the connection process. The reform programme – which has already taken almost two years – reached an important milestone in April, when Ofgem approved the new methodology, and we are now moving into the implementation phase.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from