Until the recent Court of Appeal judgment in Triple Point Technology Inc v PTT Public Company Ltd, the generally held view was that in delay cases where the contract works ...

United KingdomReal Estate and Construction

Until the recent Court of Appeal judgment in Triple Point Technology Inc v PTT Public Company Ltd, the generally held view was that in delay cases where the contract works are not completed by the original contractor, liquidated damages will be recoverable until the point of termination (at least). This is no longer the case - in the Triple Point judgment, the Court of Appeal found that in this scenario (based of course on the wording of that particular contract), the liquidated damages provision was inapplicable.

Background

  • Triple Point is a US company specialising in the design and provision of software for use in commodities trading. PTT is a company that undertakes commodities trading. In early 2013, PTT appointed Triple Point to develop, install and implement complex software. The contract provided for milestone payments and completion in stages (the Contract).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from