ARTICLE · 18 OCTOBER 2017

Projects & Construction Law Update 11 October 2017

The courts have once again shown their reluctance to hold a contract void for uncertainty, finding that the sectional completion and delay damages provisions of the relevant subcontract...

United KingdomReal Estate and Construction

Please find below Clyde & Co's latest projects and construction law update from September 2017

CASE UPDATE

But what does it mean? The court's approach to competing interpretations

Vinci Construction UK Ltd v Beumer Group UK Ltd [2017] EWHC 2196 (TCC)

The courts have once again shown their reluctance to hold a contract void for uncertainty, finding that the sectional completion and delay damages provisions of the relevant subcontract were operable and enforceable – potentially leaving the subcontractor in the lurch in respect of its liability to pay liquidated damages and the quantum thereof.

Vinci Construction UK Ltd (Vinci) subcontracted Beumer Group UK Ltd (Beumer) to design, supply and install a baggage handling system at Gatwick Airport. The subcontract works were divided into various sections, each with different completion dates and different liquidated damages that applied. Delays occurred and a dispute arose about the operation of the sectional