Please find below Clyde & Co's latest projects and
construction law update from September 2017
CASE UPDATE
But what does it mean? The court's approach to competing
interpretations
Vinci Construction UK Ltd v Beumer Group UK Ltd [2017] EWHC
2196 (TCC)
The courts have once again shown their reluctance to hold a
contract void for uncertainty, finding that the sectional
completion and delay damages provisions of the relevant subcontract
were operable and enforceable – potentially leaving the
subcontractor in the lurch in respect of its liability to pay
liquidated damages and the quantum thereof.
Vinci Construction UK Ltd (Vinci) subcontracted Beumer Group UK
Ltd (Beumer) to design, supply and install a baggage handling
system at Gatwick Airport. The subcontract works were divided into
various sections, each with different completion dates and
different liquidated damages that applied. Delays occurred and a
dispute arose about the operation of the sectional