The achievement or certification of practical completion has significant consequences under a building contract; which will usually include a release of part of the retention monies, the employer taking possession of the works and the start of the defects liability period.

United KingdomReal Estate and Construction

The achievement or certification of practical completion has significant consequences under a building contract; which will usually include a release of part of the retention monies, the employer taking possession of the works and the start of the defects liability period.

However, whilst there is an overarching principle of practical completion (PC), there is no precise legal definition; parties are free to define what practical completion will mean in their contract.

We review three TCC decisions this year and highlight the key points you need to know.

Swansea Stadium Management Company Limited v City & County of Swansea, Interserve Construction Limited [2018]

Background

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.