Introduction
The process of implementing the changes to the planning system
in Scotland is now fully underway. While the timetable has slipped
(it is some 5 years or so since the White Paper came out and over 2
years since the "new" Planning Act was passed), we now
have the National Planning Framework in its final form before the
Scottish Parliament and a published timetable which shows the
critical provisions in the legislation being implemented by Summer
2009.
One of the most significant proposals in the overhaul of the
system was the proposal to categorise developments as either
national, major or local. The consequence of this is that different
types of development will be treated in different ways and subject
to different procedures. This contrasts with the existing system
which has operated for some 60 years or so and which meant that all
applications were subject to the same procedures, if not
necessarily having the same resources applied to them.