Grove Developments Ltd v Balfour Beatty Regional Construction Ltd [2016] EWHC 168 (TCC)

Here the TCC has found that a contractor had no right to make interim payment applications once a payment schedule had expired, although the works were ongoing.

United KingdomReal Estate and Construction

Here the TCC has found that a contractor had no right to make interim payment applications once a payment schedule had expired, although the works were ongoing. The contract, worth GBP 121 million, started in July 2013 and was due to complete in July 2015, but the works were still incomplete in January 2016 when the employer sought a declaration from the court concerning the contractor's right to submit further payment applications.

The form of contract was a JCT D&B 2011, with bespoke amendments.  The parties had elected Alternative A (stage payments) and agreed a schedule of 23 interim payment applications covering the payment period.  The contractor had issued a 24th payment application in August 2015, and received an adjudicator's decision enforcing payment of it.  The employer issued part 8 proceedings, seeking a decision from the court that the contractor had no right to issue the additional payment application.  Alternatively, that it had served a pay less

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from