Here the TCC has found that a contractor had no right to make
interim payment applications once a payment schedule had expired,
although the works were ongoing. The contract, worth GBP 121
million, started in July 2013 and was due to complete in July 2015,
but the works were still incomplete in January 2016 when the
employer sought a declaration from the court concerning the
contractor's right to submit further payment applications.
The form of contract was a JCT D&B 2011, with bespoke
amendments. The parties had elected Alternative A (stage
payments) and agreed a schedule of 23 interim payment applications
covering the payment period. The contractor had issued a 24th
payment application in August 2015, and received an
adjudicator's decision enforcing payment of it. The
employer issued part 8 proceedings, seeking a decision from the
court that the contractor had no right to issue the additional
payment application. Alternatively, that it had served a pay
less