Frequently Asked Questions - JCT Design And Build Contract 2016

Wedlake Bell LLP
Wedlake Bell LLP
Contributor
Wedlake Bell LLP

Wedlake Bell LLP

Wedlake Bell provides clients with a full package of legal services delivering commercial and...

View firm profile
Explore more from Wedlake Bell LLP

JCT's stated aim was that the 2016 edition amendments do not materially affect risk allocation.

United KingdomReal Estate and Construction

Q. Has there been a change in the risk profile?

A. JCT's stated aim was that the 2016 edition amendments do not materially affect risk allocation. However it is unusual for an unamended JCT Design and Build to be used and where there is a Schedule of Amendments agreed between the parties, those amendments will themselves change the risk allocation.

Q. How will Third Party Rights (TPR's) be granted in the new edition now that this is an option for sub-contractors to grant such rights?

A. The Contract Particulars in the Articles of Agreement have been simplified by the deletion of part 2 of the Particulars. This used to set out the warranty and TPR requirements but sometimes caused confusion. Instead employers who have developed their own forms of third party rights and collateral warranty requirements can now incorporate these by reference in the Particulars. Alternatively JCT has on its website model forms for the "Rights Particulars" if the Employer does not