First Tier Tribunal Cautions Against Unreasonable Costs In Negotiating MSV Agreements Under The Electronic Communications Code

Gatehouse Chambers
Gatehouse Chambers
Contributor
Gatehouse Chambers

Gatehouse Chambers

Gatehouse Chambers is a leading commercial set with expertise spanning commercial dispute...

View firm profile
Explore more from Gatehouse Chambers

In a decision under the Electronic Communications Code, the First-Tier Tribunal denied the Respondent site provider a substantial proportion of its transactional...

United KingdomReal Estate and Construction

Cornerstone Telecommunications Infrastructure Limited v The Timberyard Plot 2 Nominee (No1) Limited and The Timberyard Plot 2 Nominee (No2) Limited

In a decision under the Electronic Communications Code, the First-Tier Tribunal denied the Respondent site provider a substantial proportion of its transactional and legal costs for the negotiation a multi-site visit agreement. The decision is warning that such costs must be reasonable and proportionately incurred amidst a background of increasing and disproportionate costs incurred by site providers

Cornerstone sought a reference under paragraph 26(1) of the Electronic Communications Code ('the Code') for the imposition of a multi-skilled visit ('MSV') agreement, following a Timberyard's failure to engage with Cornerstone over an extended period in respect of a high value property.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from