ARTICLE · 15 MAY 2008
Case Law Update - Issue 4, 2008
Keating Chambers
PC Harrington Contractors Ltd v Multiplex Constructions (UK) Ltd [2008] CILL 2544 TCC A sub-contract on the Wembley Stadium project contained provisions for interim payments. Following a dispute between main contractor Multiplex and concrete sub-contractor Harrington, Multiplex referred the matter to adjudication. Harrington argued that on the figures which it claimed were established, it should start the adjudication with £2.3 million in hand and claimed a declaration to that effect.