Supreme Court Decides on Sewer Connection

In Barratt Homes Ltd v Dwr Cymru Cyfyngedig (Welsh Water), the connection of a large new housing development to the public sewer in circumstances where the public sewer lacked the necessary capacity was considered by the Supreme Court.

United KingdomEnvironment
Aidan Thomson
Aidan Thomson

In Barratt Homes Ltd v Dwr Cymru Cyfyngedig (Welsh Water), the connection of a large new housing development to the public sewer in circumstances where the public sewer lacked the necessary capacity was considered by the Supreme Court.

Section 106 of the Water Industry Act 1991 (the "Act") grants the owner or occupier of any premises, or of any private sewer that drains premises, the right to connect to the public sewerage system.

Before connecting, the owner or occupier has to give notice to the relevant sewerage undertaker of the proposed connection. The sewerage undertaker has 21 days to object. The only basis of objection is that the mode of construction or condition of the drain or sewer does not comply with the sewerage undertaker's reasonable standards, or is such that the making of the connection would be prejudicial to the sewerage system.