The judgment in James Waste Management LLP v Essex
County Council provides insights into contract modifications
and how these may be considered against Regulation 72.
Introduction
On 19 May 2023 sitting in the Technology and Construction Court,
within the High Court of England and Wales, J Waksman handed down
his judgement in James Waste Management LLP v Essex County
Council.
The decision in question concerned whether a local authority had
lawfully modified its contract with a waste management company
under the Public Contracts Regulations 2015 (PCRs).
In terms of the facts, the Council had awarded a contract to
Veolia, with an option to extend its term (the "Veolia
Contract"). At the time this contract was entered into, it was
envisaged that a mechanical biological treatment facility would be
built and commissioned in the local area, but unfortunately that
project ultimately did not proceed, which meant that the Council
had to put alternative arrangements