Zombies To Use It Or Lose It - Implementing Electricity Connection Reform

Shepherd and Wedderburn
Shepherd and Wedderburn
Contributor
Shepherd and Wedderburn

Shepherd and Wedderburn

We are an independent law firm, headquartered in Scotland, delivering high-quality legal advice and...

View firm profile
Explore more from Shepherd and Wedderburn

Waiting times for connection to the electricity transmission system for generation projects are well publicised. Huge volumes of generation capacity are waiting in the transmission queue...

United KingdomEnergy and Natural Resources

Ofgem's CMP 376 decision addressing the electricity connections queue has practical implications for all existing and new agreements.

What is CMP 376?

Waiting times for connection to the electricity transmission system for generation projects are well publicised. Huge volumes of generation capacity are waiting in the transmission queue and projects have been offered connection dates of 2030 and beyond. This is partly due to the rise in applications for connection but is also the result of a "first come, first served" system which can lead to stalled (or "zombie") projects delaying connection timescales for other applicants.

The energy regulator for Great Britain, Ofgem, launched a policy review into electricity connections in May 2023. Several initiatives are already underway as part of the National Grid Electricity System Operator's (NGESO) five-point plan to speed up connection times, including an amnesty on Transmission Entry Capacity (TEC) charges and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from